MINUTES OF THE SPECIAL MEETING
OF THE EMERALD ISLE BOARD OF COMMISSIONERS
THURSDAY, JANUARY 15, 2004 - 6:00 PM TOWN HALL
Present for the meeting
were Mayor Art Schools, Commissioners Nita
Hedreen, Robert Isenhour, Floyd Messer, Pat McElraft, and John Wootten. Others
present were Town Manager Frank Rush, and Town Clerk Rhonda Ferebee.
Also in attendance were
representatives from Coastal Planning & Engineering, Tom Jarrett, Erin Haight,
Craig Kruempel, and Tom Campbell.
3. PRESENTATION
STATUS OF BOGUE INLET CHANNEL EROSION RESPONSE/WESTERN PHASE NOURISHMENT PROJECT
Mayor Schools welcomed
everyone to the meeting and introduced Tom Jarrett with Coastal Planning &
Engineering.
The staff of Coastal
Planning & Engineering gave a PowerPoint presentation of the status of the Bogue
Inlet Channel Erosion Response Project. (A copy of this report is attached
and incorporated into these minutes). The following is the outline of
topics discussed for the Board:
Presentation Outline
a.
Introduction of Coastal Planning &
Engineering Team
b.
Contract Scope and Compensation
c.
Work Completed to Date
d.
Review of Preliminary Project
Design/Issues
e.
Remaining Work/Project Schedule
f.
Review of Project Budget
g.
The Future of Bogue Inlet
Mr. Jarrett explained that
the purpose of the meeting tonight was aimed at bringing the new Board of
Commissioners up-to-date on the status of the Bogue Inlet Channel Erosion
Response Project. Mr. Jarrett introduced others with Coastal Planning &
Engineering involved with this particular project for Emerald Isle beginning
with their President and Founder Tom Campbell, Craig Kruempel, and Erin Haight
all from the Boca Raton office.
Mr. Jarrett noted the key
dates and events beginning in May of 2002 when Coastal Planning & Engineering
was selected by the Town. He said they met in August of 2002 with the State and
Corps to review the EIS preparation. It was at that time that the Town decided
rather than try to go the Environmental Assessment route, knowing the input from
the resource agencies at the May meeting, they decided they wanted to pursue a
full Environmental Impact Statement. He noted that decision was driven
primarily by the experience that New Hanover
County had with the Mason Inlet Project, and the demands that were put on New
Hanover to respond to environmental and engineering concerns associated with
that particular project. He continued to list other key dates and events up to
December 26, 2003 which was the close of
public comment period on the Draft Environmental Impact Statement.
Mr. Jarrett noted the tasks
completed as follows:
- Engineering, Geological,
and Geomorphic Report April 2003
- Draft Biological
Assessment July 2003
- Final Essential Fish
Habitat Analysis September 2003 (included in DEIS)
- Revised Cumulative
Effects Assessment to Corps October 2003 (included in DEIS)
- Draft EIS released for
public review and comment November 7, 2003.
Mr. Jarrett noted that we
are still moving along on a schedule that still has the Town obtaining a Corps
and State permit in August of 2004.
Mr. Jarrett noted the
remaining tasks as follows:
- February 19, 2004
Submit revised EIS to Corps and State for review
- March 11-12, 2004
Meeting with Corps and State to review comments
- March 25, 2004 Corps
releases revised FEIS for public review and comment.
- May 23, 2004 Corps
publishes Record of Decision
- August 8, 2004 State
issues CAMA permit.
- August 28, 2004 Corps
issues permit
- August 29, 2004
Advertise project for construction
- November 15, 2004 to
February 21, 2005 Construction period
Mr. Jarrett gave a brief
summary of contract details as follows:
- Original contract amount
- $385,700
- Contract amount revised
in January 2003 to include pre-project environmental monitoring identified by
PDT Amount of contract modification - $105,000
- Contract amount revised
in May 2003 to include added CPE cost ($170,000) and additional habitat
mapping and ground truth ($101,400) identified by PDT.
- Added CPE costs due to
project coordination, environmental tasks, and project design.
Mr. Jarrett outlined the
Plan Formulation which included the following:
- Problem Identification
- Geotechnical Analysis
- Channel Design
- Alternative
The following environmental
impacts for the preferred alternative were listed as follows:
- Apart from physical
changes, environmental impacts predicted to be minimal.
- Only identified direct
impact would be the net loss of shallow bottom habitat due to channel
construction and dike construction.
- Existing channel
expected to fill over 4 to 5 years replacing shallow bottom habitat.
- Town will be required to
monitor project impacts and mitigate if project related impacts identified.
Mr. Jarrett, introduced
Erin Haight, Lead Project Scientist with Coastal Planning & Engineering.
Ms. Haight described in
great detail to the Board the biological monitoring requirements (bird, salt
marsh, and macroinvertebrates/Infauna), schedules, and commitments for the Town
of Emerald Isle Bogue Inlet Channel Erosion Response Project. (A copy of the
Proposed Monitoring/Mitigation Plan including an estimate of probable cost is
attached and incorporated into these minutes.)
Town Manager Frank Rush
discussed with the Board the Proposed Monitoring/Mitigation Plan, most
specifically the last page,the Estimate of Probable Cost. He said this spread
sheet outlined timelines and costs associated with what they project the
monitoring requirement will be for the next five years. He noted the bottom
line of project cost was $468,000. There is currently a total available budget
for monitoring of $200,000, which means we are $268,000 short right now. He
added that this doesnt include some of the
things being covered by the
County Shore Protection Officer, for example the beach profile surveys that are
done, as well as the turtle monitoring. Mr. Rush said that fortunately the
Environmental Impact Statement does not predict any negative impact on the
resources so they feel confident that it will not become an issue but he wanted
the Board to be aware that there is the potential risk should something
different occur than what is predicted by the EIS.
Mr. Rush advised the Board
that there was some additional consideration being given by the United States
Fish and Wildlife Service and the North Carolina Wildlife Resources Commission
regarding the bird management plan and also possibly replacing some of this
monitoring noted on this sheet with some research done by UNC-W or some other
research institutions, so it is still a work in progress. He thought this would
probably be finalized in the permit conditions from the Corps and the Division
of Coastal Management.
Mr. Rush pointed out to the
Board regarding the Bird Management Plan, the basic concept that has been
discussed is delineating an area on the spit that would be protected, and
designated as a bird habitat. He said this would probably be marked by ropes or
signs informing the public about the sensitive bird habitat in that area, and
there would be some type of enforcement action associated with that. He said
the North Carolina Wildlife Resource Commission and the Fish and Wildlife
Service were currently working a proposal to accomplish some of the management
goals out there.
Mr. Rush advised the Board
that the total construction budget was $4,150,000 which is for the mobilization
of the dredge, the demobilization and also the pumping costs. He added that Mr.
Jarret believed that the figures used in calculating this budget were
reasonable.
There was a short question
and answer/Board comment session following Mr. Jarretts presentation.
Mayor Schools called
for adjournment at 8:10 p.m.
Respectfully submitted:
Rhonda C. Ferebee
Town Clerk
|