Reed Dr Drainage

Nov

2023

Construction End

Aug

2023

Construction Start

Jan

2023

Pre-Construction Meeting

Overview

Project zone is located along Reed Dr. between East Seaview and Mangrove Drive.  Town staff will install pipes and pump station to create underground storage for stormwater collection to reduce the duration of and help mitigate nuisance street flooding and potential property damage. 

This project is funded through FEMA 428 grant money. This stormwater project was funded at $289,000.

Timeline

Project Start Date: April 20, 2023

Projected End Date: November 15, 2023

Status: Delivery Accepted

Next Step: Under Construction

ReedDrInfiltration

Staff Contact: 

Joe Smith, Public Works Director

Email Joe Smith, Public Works Director

252-354-4450

Contractor:

Town of Emerald Isle Staff