Lee Ave Culvert

May

2023

Construction End

Apr

2023

Construction Start

Jan

2023

Pre Construction Meeting

Jan

2023

Contract Awarded

Dec

2022

Out for Bid

Overview

The project zone is located between Emerald Dr. and Sound Dr. on Lee Avenue.  Contractors will replace culvert where Lee Ave. crosses Archers Creek. 

This project was awarded to Thomas Simpson Construction Company, and is funded through FEMA 428 grant money. This stormwater project was awarded at $115,600.

Timeline

Project Start Date: April 20, 2023

Projected End Date: May 20, 2023

Status: Awaiting Materials  

Next Step: Under Construction

LeeAveCulvert3

Staff Contact: 

Joe Smith, Public Works Director

Email Joe Smith, Public Works Director

252-354-4450

Contractor:

Thomas Simpson Construction Company