Timeline
Project Start Date: Q4 2023 or Q1 2024
Projected End Date: 90 days following construction start
Status: Under Construction
Next Step: Construction End
Project Updates
The concrete curb and driveway work is complete north of the creek crossing. 12/8 Crews are working on the Southside curbing and cleaning up the coffer dam material. The street will be open temporarily for the coming weekend (12/9 - 12/10). The week of January 11th, crews will return to remove a protion of the street within the work zone and begin the regrading and paving process.