Cedar Street Culvert Replacement

Feb

2024

Construction End

Nov

2023

Construction Start

Oct

2023

Pre Construction Meeting

Sep

2023

Contract Awarded

Jul

2023

Out for Bid

Overview

The project zone is located between Emerald Dr. and Sound Drive. Contractors will replace failing culvert at creek crossing on Cedar Street.  Due to environmental, CAMA, and FEMA regulations, the pipe will be replaced with a "like for like" drainage culvert.

This project was awarded to Thomas Simpson Construction Company, and is funded through FEMA 428 grant money. This stormwater project was awarded at $212,865.

Timeline

Project Start Date: Q4 2023 or Q1 2024

Projected End Date: 90 days following construction start

Status: Under Construction  

Next Step: Construction End


Project Updates

The concrete curb and driveway work is complete north of the creek crossing. 12/8 Crews are working on the Southside curbing and cleaning up the coffer dam material. The street will be open temporarily for the coming weekend (12/9 - 12/10).  The week of January 11th, crews will return to remove a protion of the street within the work zone and begin the regrading and paving process.

CedarStreetCulvert1

Staff Contact: 

Joe Smith, Public Works Director

Email Joe Smith, Public Works Director

252-354-4450

Contractor:

Thomas Simpson Construction Company