Bogue Inlet Culvert Replacement

Sep

2023

Contract Awarded

Aug

2023

Pre-Construction Meeting

Jul

2023

Out for Bid

Overview

The project zone is located between Emerald Dr. and Sound Drive. Contractors will replace failing culvert at creek crossing on Bogue Inlet Drive.  Due to environmental, CAMA, and FEMA regulations, the pipe will be replaced with a "like for like" drainage culvert.  

This project was awarded to Thomas Simpson Construction Company, and is funded through FEMA 428 grant money. This stormwater project was awarded at $171,045.

Timeline

Project Start Date: Q4 2023 or Q1 2024

Projected End Date: 90 days following start of construction

Status: Contract Awarded 

Next Step: Construction Start 

BogueInletCulvert2

Staff Contact: 

Joe Smith, Public Works Director

Email Joe Smith, Public Works Director

252-354-4450

Contractor:

Thomas Simpson Construction Company